7-8 St. Martins Place

Project:
7-8 St. Martins Place
Location:
This is some text inside of a div block.
Duration:
65 Weeks
Value:
£2,800,000.00
Nature:
This is some text inside of a div block.
Client:
De-Specialist Works

About the Project

Deploy UK Ltd assisted De-Specialist Works in delivering the structural alterations package at 7-8 St. Martins Place, where a new hotel was to be created.

The scope of works included:

• Soft Strip to Common Areas

• Demolition to Existing Roof Plant Structures and removal of finishes

• Construction of a new 2 storey steel roof extension

• Composite slab installation to new floor levels

• Extension of existing lift cores and overruns to service new floor levels

• Installation of 5nr steel staircases throughout

• New below ground drainage

• New reinforced concrete basement slab

• Cavity drain system

• Screeding

• New reinforced concrete lift pit and steel lift shaft (Basement to roof)

• Miscellaneous steel installations.

Labour Supplied

• Handyman

• General Labour

• CCDO Demolition Labourers

• Machine Drivers

• Carpenters

• Groundworkers